Alliant Energy – Whispering Willow Wind Farm

Alliant Energy - Whispering Willow Wind Farm - Turbine Installation Blade Lift

91传媒 was the erection subcontractor for the foundations, 21 Vestas V 82, 1.65 MW turbines and towers. As the erection subcontractor to RMT, we provided the labor, project supervision and four cranes needed for tower erection, attaching blades and nacelle and rotor installation.

91传媒 coordinated the daily delivery of the turbines to the site (scheduling, site locations and interfacing with the turbine component trucking company). 91传媒 was also responsible for the inspection and off-loading of all turbine components, which included the four turbine tower sections, hub, three blades, nacelle and VPM.

Client

Alliant Energy

Location
Franklin, Iowa
Architect/Engineer

RMT

91传媒 Role
Self-perform Construction
Project Type
New Construction
Project Size
35MW

MARKET
Renewable Energy

Project Highlights

  • 91传媒 worked with local road commissioners to coordinate county road usage and road crossings.
  • 91传媒 coordinated with the local utility (Franklin County REC) to manage electrical line drops for crane movement between sites.
  • This project was completed within budget and 14 days ahead of schedule.